Hi All
Any User using excel for Project Planning ? How can you calcuate Start
date and End date base on given Start date. The calcuation not include
Sunday and Saterday. Any Suggestion ?
Example
http://www.editgrid.com/user/cxleung/Planning
moonhk
GMT+8
carlo - 21 Nov 2007 07:45 GMT
Check the Help for Networkdays.
hth Carlo