I am tracking a 5 day sporting event that has stages and
legs within the stage.
I am estimating the time it will take to complete a leg,a
stage and a cumulative time. I input the leg time, have
excel calculate the stage time and the cumulative time.
My problem is when a day rolls over ( 24 hours have
elapsed since the start).
The cumulative result goes back to 0:00 and starts from
scratch.
How can I have the cumulative time accuratly show the
a/ actual elapsed time or
b/ the day and lapsed time for that day.
cheers
Mike
Norman Harker - 14 Apr 2004 04:41 GMT
Hi Mike!
Format the total:
[hh]:mm:ss

Signature
Regards
Norman Harker MVP (Excel)