Tera,
Set up two cells and name them StartDate and EndDate. This is set up for
StartDate of Monday.
B1: =StartDate
C1: ==IF(B1<>"",IF(B1+1<=EndDate,B1+1,""),"")
Copy (Fill Handle) to F1.
You now have one week, based on start and end dates.
G1: =IF(F1<>"",IF(F1+3<=EndDate,F1+3,""),"") Monday date
Copy C1:F1, paste to H1:K1.
You now have the second week of date formulas, G1:K1, Mon-Fri
Copy G1:K1, paste from L1 to right edge of worksheet:
Select and Copy G1:K1. Copy.
Select L1, Ctrl-Shift-RightArrow
Paste.